Main Street Improvements – Olathe, CO

Main Street Improvements – Olathe, CO

Project Description:  This project consisted of the complete re-build of the east end of Main Street in Olathe, CO.  Some of the key components of this project were milling of the existing asphalt, excavation to new sub-grades, installation of a new waterline, reconnection of existing water services to new water main, new 8 inch and 6 inch gate valves, new fire hydrant, placement of new curb, gutter and sidewalks, road base, ADA ramps and landscaping fabric and rock.

Contract Amount:  $307,059

Project Duration:  3 1/2 Months